Escalation clause
An escalation clause is a provision that may be included in a construction contract to allow for adjustments in the contract price based on fluctuations in the cost of materials, labour, or other project-related expenses. This clause is designed to manage the risk associated with price volatility over the duration of a project. Escalation clauses are commonly used in long-term projects or those involving significant amounts of raw materials that are subject to market fluctuations. They are particularly relevant in times of economic instability or high inflation.
The primary purpose is to protect both the contractor and the client from the financial impact of significant cost changes that could not have been anticipated at the time of contract signing. It ensures that contractors are not unfairly penalised by unforeseen price increases and that clients are not overcharged.
The clause typically specifies the conditions under which price adjustments can be made. Common triggers include:
- Increases in the cost of materials.
- Changes in labour costs due to new wage agreements or labour shortages.
- Variations in fuel or transportation costs.
Escalation clauses may be calculated based on:
- A predetermined percentage increase at specified intervals.
- Adjustments based on actual cost changes, with detailed documentation.
- Adjustments based on specific cost indexes relevant to the construction industry.
This provides a transparent and objective method for determining the price changes. The contract will also outline how often price adjustments can be made. This might be on a monthly, quarterly, or milestone basis, depending on the length and nature of the project.
To prevent excessive adjustments, escalation clauses may include caps or limits on the amount by which the contract price can be increased. This protects clients from unlimited cost escalation and provides a clear framework for managing potential increases.
The contractor is usually required to provide detailed documentation supporting any claimed increases, and there may be a requirement for prior notification before adjustments are applied. This ensures transparency and allows for verification by the client or their representatives.
See also: Fluctuations and Escalation.
[edit] Related articles on Designing Buildings
Featured articles and news
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.